top of page

Produced a complete, permit-ready site plan package and enhanced coordination efficiency between design engineers, the client, and the reviewing county.

Impact:

  • Conducted an on-site evaluation to assess grading and circulation needs.

  • Converted survey data into Bohler CAD standards and modeled the buildings and utilities in AutoCAD Civil 3D.

  • Designed water, sanitary, and storm systems that met slope and environmental requirements.

  • Created fire access and slope banding exhibits to confirm compliance and improve client communication.

Solution:

Develop a code-compliant site plan for a new warehouse complex while balancing grading, utility layout, and emergency access within strict county design and environmental standards.

Challenge:

(AutoCAD Civil 3D, Site Design, Grading & Utilities)

Brookfield Warehouses

1.jpg
7.jpg

Delivered efficient, code-compliant site layouts that improved functionality and gained quick client approval. Strengthened technical CAD design, problem-solving, and interdisciplinary coordination skills.

Impact:

  • Standardized survey data and CAD layers to meet Bohler design conventions.

  • Designed and optimized parking, truck circulation, and loading layouts to ensure safe, efficient site operation.

  • Produced concept plans, submission sheets, and code exhibits for client and county review.

  • Conducted a sanitary sewer flow analysis for Vinson Hall using GIS data and Excel modeling to identify necessary pipe replacements.

  • Implemented client feedback and streamlined the revision process to meet submission timelines.

Solution:

Support multiple commercial and institutional projects each with unique circulation, utility, and code compliance requirements under tight deadlines and evolving client needs.

Challenge:

(Versar Auto Dealership, Costco Winchester, Vinson Hall Senior Living, Walmart Sterling & Alexandria, Tysons Station, CMA Martinsburg)

Site Design Projects

bottom of page